Phase

Execution

On track

Progress

45%

by working days

Forecast

1369

k€ · approved 1082 · +287

Phaseany phasePackageall packagesContractoranyoneShowing44 activities · 45% done
StepWhoWhenDaysDone
Initiation6 Jun12 Jun1 of 1 done
Bid + 40% estimateF. de Boer7 Jun%
Definition6 Jun11 Sep3 of 4 done
Scope and basis of designF. de Boer6 Jun15 Jun7%
Concept drawingsH. Nawrocki18 Jun29 Jun9%
Cost estimate ±25%C. Peeters30 Jun5 Jul5%·
Basic engineering + scrub + 25% estimateH. Nawrocki6 Sep%
Preparation10 Sep13 Oct7 of 7 done
Detail engineeringHelder E&I13 Sep2 Oct14%
Isometrics and material take-offPrometheus Piping3 Oct10 Oct6%
Permit applicationI. Abdi11 Oct13 Oct1%
Permit lead timewaitingPO-45002466M. Bakker14 Oct7 Nov%
Tender and awardS. de Vries10 Nov24 Nov10%
Long lead items on orderwaitingPO-45002468Helder E&I25 Nov3 Jan%
Detail engineering + 10% estimateC. Peeters8 Oct%
Execution13 Oct9 Jul15 of 41 done
Insulation and paintingPrometheus Piping13 Oct16 Oct4%·
TK 101E. Vermeulen13 Oct15 Nov25%
Reinstate, clean and hand backVan Dijk Industrial18 Oct19 Oct0%
MC punch walk with operationsJ. Visser20 Oct20 Oct1%
TK 102Van Dijk Industrial4 Nov7 Dec24%
TK 103H. Nawrocki26 Nov29 Dec24%
TK 104C. Peeters18 Dec20 Jan24%·
TK 2101Helder E&I8 Jan10 Feb24%
TK 2005G. Smits30 Jan4 Mar24%
TK 2003I. Abdi21 Feb26 Mar24%
TK 2001Nordkraft Montage15 Mar17 Apr25%
TK 1907S. de Vries6 Apr9 May25%
TK 1906R. Janssen28 Apr31 May24%
TK 1905Prometheus Piping20 May22 Jun24%·
TK 1904L. Haddad10 Jun13 Jul24%
TK 1903J. Visser2 Jul4 Aug24%
TK 1902Baird Mechanical24 Jul26 Aug24%
TK 1901K. van Dijk15 Aug17 Sep24%
TK 1814P. Hoekstra6 Sep9 Oct25%
TK 1813Van Dijk Industrial28 Sep31 Oct25%
TK 1812D. Kramer20 Oct22 Nov24%
TK 1811E. Vermeulen11 Nov14 Dec24%
TK 1810Helder E&I2 Dec4 Jan24%
TK 1809H. Nawrocki24 Dec26 Jan24%
TK 1808C. Peeters15 Jan17 Feb24%
TK 1807Nordkraft Montage6 Feb11 Mar24%
TK 1806G. Smits28 Feb2 Apr25%
TK 1804I. Abdi22 Mar24 Apr25%
TK 1803Prometheus Piping13 Apr16 May24%
TK 1802S. de Vries4 May6 Jun24%
Tender + long leadsW. van Leeuwen25 May%
TK 1801R. Janssen26 May28 Jun24%
Work plansI. Abdi4 Jun%
RFCG. Smits5 Jun+6d%
LOTO plansM. Bakker9 Jun%
Start constructionS. de Vries14 Jun%
TK 1712Baird Mechanical17 Jun9 Jul17%
MCR. Janssen19 Jun%
RFOL. Haddad29 Jun%
RFO formsJ. Visser4 Jul%
CommissioningT. Okonkwo5 Jul+11d%
Close-out13 Jul11 Oct0 of 8 done
Punch list clearingBaird Mechanical14 Jul21 Jul6%
As-built and handover fileK. van Dijk22 Jul27 Jul4%
Financial closureP. Hoekstra31 Jul4 Aug3%
Punch listunassigned16 Sep%
Evaluationunassigned26 Sep%
As-builtunassigned27 Sep+6d%
Financialunassigned1 Oct%
Close-outunassigned6 Oct%