| Phase / kind | Step | Owner | Date | Done | Note |
|---|---|---|---|---|---|
| Identification | PRJ-0031Building maintenanceOn hold | I. Abdi | 25 Jul 26 | 15% | 74 → 74 k€0.0% |
| Identification | PRJ-0032Pig catcher replacementOn track | M. Bakker | 28 Jul 26 | 35% | 268 → 268 k€0.0% |
| Identification | PRJ-0049Bund wall repairsOn hold | R. Janssen | 25 Jul 26 | 15% | 579 → 579 k€0.0% |
| Identification | PRJ-0050Preventive maintenance backlogOn track | A. Mulder | 10 Nov 26 | 35% | 42 → 42 k€0.0% |
| Identification | PRJ-0059TK 1902 - mixer overhaulOn hold | W. van Leeuwen | 25 Jul 26 | 15% | 391 → 391 k€0.0% |
| Identification | PRJ-0093Loading arm renovationOn track | K. van Dijk | 6 Nov 26 | 55% | 241 → 241 k€0.0% |
| Identification | PRJ-0098Civil repairs roads-pavementsOn track | F. de Boer | 12 Aug 26 | 35% | 900 → 900 k€0.0% |
| Identification | PRJ-0100Install lifting equipment manifold bayOn track | R. Janssen | 11 Sep 26 | 70% | 599 → 599 k€0.0% |
| Identification | PRJ-0101Jetty repairOn track | T. Okonkwo | 28 Aug 26 | 80% | 665 → 665 k€0.0% |
| Identification | PRJ-0103Retaining wall repairsOn track | J. Visser | 27 Jul 26 | 95% | 613 → 613 k€0.0% |
| Identification | PRJ-0104Replacement underground firewater pipelinesOn track | A. Mulder | 9 Oct 26 | 35% | 641 → 641 k€0.0% |
| Identification | PRJ-0106Concrete repairs to roads and hardstandingOn track | P. Hoekstra | 5 Jan 27 | 70% | 418 → 418 k€0.0% |
| Identification | PRJ-0109Earthing structures and pipelinesOn track | E. Vermeulen | 18 Aug 26 | 95% | 248 → 248 k€0.0% |
| Identification | PRJ-0113Replace flowtransmitters jetty -02On track | M. Bakker | 17 Nov 26 | 35% | 317 → 317 k€0.0% |
| Identification | PRJ-0114Maintenance activities offices and buildingsOn track | S. de Vries | 28 Jul 26 | 55% | 88 → 88 k€0.0% |
| Identification | PRJ-0115Pipework replacementOn track | R. Janssen | 10 Jul 26 | 70% | 116 → 116 k€0.0% |
| Identification | PRJ-0116On-site pipeline inspectionOn hold | T. Okonkwo | 25 Jul 26 | 15% | 351 → 351 k€0.0% |
| Identification | PRJ-0117On-site pipeline maintenanceOn track | L. Haddad | 28 Jul 26 | 90% | 301 → 301 k€0.0% |
| Identification | PRJ-0118Pipe sleeves/penetrations replacementOn track | J. Visser | 28 Jul 26 | 95% | 304 → 304 k€0.0% |
| Identification | PRJ-0119Renovation marine loading armsOn track | A. Mulder | 28 Jul 26 | 35% | 306 → 306 k€0.0% |
| Identification | PRJ-0120Pig catcher replacementOn track | D. Kramer | 28 Jul 26 | 90% | 156 → 156 k€0.0% |
| Identification | PRJ-0121Nitrogen blanketingOn hold | E. Vermeulen | 25 Jul 26 | 15% | 186 → 186 k€0.0% |
| Identification | PRJ-0122Waste water process improvementOn track | F. de Boer | 28 Jul 26 | 35% | 161 → 161 k€0.0% |
| Identification | PRJ-0123TK 1906 - floating roof seal replacementOn track | H. Nawrocki | 28 Jul 26 | 55% | 229 → 229 k€0.0% |
| Identification | PRJ-0124In Service (On Stream) InspectionsOn track | C. Peeters | 28 Jul 26 | 70% | 232 → 232 k€0.0% |
| Identification | PRJ-0125TK 1907 - shell plate repairsOn track | W. van Leeuwen | 28 Jul 26 | 80% | 236 → 236 k€0.0% |
| Identification | PRJ-0126Replacement P8 water treatmentOn track | G. Smits | 28 Jul 26 | 90% | 103 → 103 k€0.0% |
| Identification | PRJ-0127Gas detection installationOn track | I. Abdi | 28 Jul 26 | 95% | 196 → 196 k€0.0% |
| Identification | PRJ-0128Portfolio contingencyOn hold | M. Bakker | 25 Jul 26 | 15% | 173 → 173 k€0.0% |
| Identification | PRJ-0129TK 0214: (Out-of-service) inspection & TTAROn track | S. de Vries | 28 Aug 26 | 55% | 159 → 159 k€0.0% |
| Identification | PRJ-0130Tk 0215: (Out-of-service) inspection & TTAROn track | J. Visser | 11 Sep 26 | 95% | 209 → 209 k€0.0% |
| Identification | PRJ-0131TK 0307: (Out-of-service) inspection & TTAROn track | A. Mulder | 21 Oct 26 | 35% | 203 → 203 k€0.0% |
| Identification | PRJ-0132TK 0314: (Out-of-service) inspection & TTAROn track | K. van Dijk | 9 Oct 26 | 55% | 214 → 214 k€0.0% |
| Identification | PRJ-0133Tk 0317: (Out-of-service) inspection & TTAROn track | P. Hoekstra | 9 Oct 26 | 70% | 216 → 216 k€0.0% |
| Identification | PRJ-0134TK 0502: (Out-of-service) inspection & TTAROn track | N. Yilmaz | 25 Sep 26 | 80% | 241 → 241 k€0.0% |
| Identification | PRJ-0135TK 0504: (Out-of-service) inspection & TTAROn track | D. Kramer | 7 Aug 26 | 90% | 327 → 327 k€0.0% |
| Identification | PRJ-0138TK 1316: (Out-of-service) inspection & TTAROn track | H. Nawrocki | 29 Mar 27 | 55% | 234 → 234 k€0.0% |
| Identification | PRJ-0139TTAR Tank 1408On hold | C. Peeters | 25 Jul 26 | 15% | 424 → 424 k€0.0% |
| Identification | PRJ-0140TK 1604: (Out-of-service) inspection & TTAROn track | M. Bakker | 28 Jul 26 | 35% | 287 → 287 k€0.0% |
| Identification | PRJ-0141TK 1612: (Out-of-service) inspection & TTAROn track | S. de Vries | 5 Jan 27 | 55% | 290 → 290 k€0.0% |
| Identification | PRJ-0142TK 1805: (Out-of-service) inspection & TTAROn track | R. Janssen | 16 Apr 27 | 70% | 296 → 296 k€0.0% |
| Identification | PRJ-0144TK 1807: (Out-of-service) inspection & TTAROn track | L. Haddad | 6 Nov 26 | 90% | 301 → 301 k€0.0% |
| Identification | PRJ-0145TK 2005: On-Stream inspectionOn track | J. Visser | 28 Jul 26 | 95% | 457 → 457 k€0.0% |
| Identification | PRJ-0146TK 2202: (Out-of-service) inspection & TTAROn track | A. Mulder | 13 Apr 27 | 35% | 422 → 422 k€0.0% |
| Identification | PRJ-0154Painting and coating programmeOn hold | I. Abdi | 25 Jul 26 | 15% | 55 → 55 k€0.0% |
| Identification | PRJ-0157Study and front-end engineeringOn hold | R. Janssen | 25 Jul 26 | 15% | 200 → 200 k€0.0% |
| Identification | PRJ-0164Building maintenanceOn hold | F. de Boer | 25 Jul 26 | 15% | 300 → 700 k€+133.5% |
| Identification | PRJ-0168Painting and coating programmeOn track | G. Smits | 28 Jul 26 | 90% | 68 → 68 k€0.0% |
| Identification | PRJ-0174Lifting equipment inspectionOn track | K. van Dijk | 28 Jul 26 | 55% | 84 → 84 k€0.0% |
| Identification | PRJ-0200Fence renewalOn track | N. Yilmaz | 10 Nov 26 | 80% | 550 → 550 k€0.0% |
| Identification | PRJ-0201BundwallsOn track | D. Kramer | 13 Oct 26 | 90% | 540 → 540 k€0.0% |
| Identification | PRJ-0204Repl. Part wastwatersewer pipelinesOn track | H. Nawrocki | 12 Oct 26 | 55% | 482 → 482 k€0.0% |
| Identification | PRJ-0205Replacement underground firewater pipelinesOn track | C. Peeters | 9 Apr 27 | 70% | 459 → 459 k€0.0% |
| Identification | PRJ-0207Retaining wall repairsOn track | G. Smits | 11 Feb 27 | 90% | 378 → 378 k€0.0% |
| Identification | PRJ-0210Earthing and bonding surveyOn track | L. Haddad | 17 Nov 26 | 90% | 214 → 214 k€0.0% |
| Identification | PRJ-0214Replace tourniquetOn track | P. Hoekstra | 28 Jul 26 | 70% | 80 → 80 k€0.0% |
| Identification | PRJ-0215On-site pipeline inspectionOn hold | N. Yilmaz | 25 Jul 26 | 15% | 315 → 315 k€0.0% |
| Identification | PRJ-0216On-site pipeline maintenanceOn hold | D. Kramer | 25 Jul 26 | 15% | 318 → 318 k€0.0% |
| Identification | PRJ-0217SHEQ improvement budgetOn track | E. Vermeulen | 28 Jul 26 | 95% | 273 → 273 k€0.0% |
| Identification | PRJ-0218Actions out of HAZOPOn track | F. de Boer | 28 Jul 26 | 35% | 276 → 276 k€0.0% |
| Identification | PRJ-0219In Service (On Stream) InspectionsOn hold | H. Nawrocki | 25 Jul 26 | 15% | 458 → 458 k€0.0% |
| Identification | PRJ-0220Install floating roof seals'TK 708/809/810On track | I. Abdi | 28 Jul 26 | 95% | 468 → 468 k€0.0% |
| Identification | PRJ-0221TK 0202: (Out-of-service) inspection & TTAROn track | M. Bakker | 31 Jul 26 | 35% | 249 → 249 k€0.0% |
| Identification | PRJ-0223TK 0209: (Out-of-service) inspection & TTAROn track | R. Janssen | 19 Feb 27 | 70% | 253 → 253 k€0.0% |
| Identification | PRJ-0224TK 0312: (Out-of-service) inspection & TTAROn track | T. Okonkwo | 23 Oct 26 | 80% | 286 → 286 k€0.0% |
| Identification | PRJ-0225TK 0505: (Out-of-service) inspection & TTAROn track | L. Haddad | 25 Sep 26 | 90% | 265 → 265 k€0.0% |
| Identification | PRJ-0227TK 0909: (Out-of-service) inspection & TTAROn track | A. Mulder | 28 Apr 27 | 35% | 384 → 384 k€0.0% |
| Identification | PRJ-0228TK 0910: (Out-of-service) inspection & TTAROn track | K. van Dijk | 9 Oct 26 | 55% | 385 → 385 k€0.0% |
| Identification | PRJ-0234Building maintenanceOn hold | G. Smits | 25 Jul 26 | 15% | 60 → 60 k€0.0% |
| Identification | PRJ-0241Replacement MCC's pump roomsOn track | P. Hoekstra | 19 Mar 27 | 70% | 1261.4 → 3212 k€+154.7% |
| Identification | PRJ-0242TK 310 - internal coating renewalOn track | N. Yilmaz | 28 Jul 26 | 80% | 407 → 407 k€0.0% |
| Identification | PRJ-0254Mixer Tank 207On track | A. Mulder | 6 Nov 26 | 35% | 29 → 29 k€0.0% |
| Identification | PRJ-0259Painting and coating programmeOn hold | E. Vermeulen | 25 Jul 26 | 15% | 50 → 50 k€0.0% |
| Identification | PRJ-0261Emergency shower replacementOn hold | G. Smits | 25 Jul 26 | 15% | 67 → 67 k€0.0% |
| Identification | PRJ-0266TK 406 - roof drain replacementOn track | T. Okonkwo | 6 Nov 26 | 80% | 257 → 257 k€0.0% |
| Identification | PRJ-0272Lifting equipment inspectionOn hold | F. de Boer | 25 Jul 26 | 15% | 89 → 89 k€0.0% |
| Identification | PRJ-0278Hydrant replacementOn track | M. Bakker | 28 Jul 26 | 35% | 80 → 80 k€0.0% |
| Identification | PRJ-0279Civil repairs roads-pavementsOn track | S. de Vries | 13 Oct 26 | 55% | 983 → 983 k€0.0% |
| Identification | PRJ-0280Concrete plates railOn track | J. Visser | 28 Jul 26 | 95% | 45 → 45 k€0.0% |
| Identification | PRJ-0282Stairways and handrailing adjust/addOn track | K. van Dijk | 28 Jul 26 | 55% | 46 → 46 k€0.0% |
| Identification | PRJ-0284Fire water pump repairOn track | N. Yilmaz | 28 Jul 26 | 80% | 47 → 47 k€0.0% |
| Identification | PRJ-0286Camera system replacementOn track | E. Vermeulen | 28 Jul 26 | 95% | 231 → 231 k€0.0% |
| Identification | PRJ-0289Fence repairOn track | C. Peeters | 28 Jul 26 | 70% | 64 → 64 k€0.0% |
| Identification | PRJ-0290Maintenance Activities Offices and BuildingsOn track | M. Bakker | 28 Jul 26 | 35% | 80 → 80 k€0.0% |
| Identification | PRJ-0291On-site pipeline inspectionOn hold | S. de Vries | 25 Jul 26 | 15% | 318 → 318 k€0.0% |
| Identification | PRJ-0292On-site pipeline maintenanceOn hold | R. Janssen | 25 Jul 26 | 15% | 321 → 321 k€0.0% |
| Identification | PRJ-0293Study N2 bufferingOn track | T. Okonkwo | 28 Jul 26 | 80% | 276 → 276 k€0.0% |
| Identification | PRJ-0294In service (On Stream) InspectionsOn hold | L. Haddad | 25 Jul 26 | 15% | 458 → 458 k€0.0% |
| Identification | PRJ-0295TK S3: (Out-of-service) inspection & TTAROn track | J. Visser | 27 Jan 27 | 95% | 196 → 196 k€0.0% |
| Identification | PRJ-0297TK 0115: (Out-of-service) inspection & TTAROn track | K. van Dijk | 21 Aug 26 | 55% | 225 → 225 k€0.0% |
| Selection | PRJ-0014Fire proofing of structuresOn track | F. de Boer | 14 Aug 26 | 35% | 1420 → 1420 k€0.0% |
| Selection | PRJ-0018Oxygen monitoring installationOn track | G. Smits | 6 Nov 26 | 90% | 528 → 528 k€0.0% |
| Selection | PRJ-0108Cable tray renewalOn track | D. Kramer | 11 Aug 26 | 90% | 271 → 271 k€0.0% |
| Selection | PRJ-0181Loading arm renovationOn track | I. Abdi | 20 Aug 26 | 95% | 156 → 156 k€0.0% |
| Selection | PRJ-0198Oxygen monitoring installationOn track | S. de Vries | 6 Aug 26 | 55% | 470 → 470 k€0.0% |
| Definition | PRJ-0025Replace parts of cable trays on main cableOn track | P. Hoekstra | 31 Jul 26 | 70% | 328 → 328 k€0.0% |
| Definition | PRJ-0035Pipework replacementOn track | T. Okonkwo | 10 Nov 26 | 80% | 266 → 266 k€0.0% |
| Definition | PRJ-0039Retaining wall repairsOn track | K. van Dijk | 11 Sep 26 | 55% | 1025 → 1025 k€0.0% |
| Definition | PRJ-0042CP Upgrade off-site PipelinesOn track | H. Nawrocki | 6 Nov 26 | 55% | 843 → 843 k€0.0% |
| Definition | PRJ-0097Bund wall repairsOn track | E. Vermeulen | 7 Aug 26 | 95% | 1069 → 1069 k€0.0% |
| Definition | PRJ-0099Contractor housingOn track | H. Nawrocki | 6 Nov 26 | 55% | 1028 → 1028 k€0.0% |
| Definition | PRJ-0102Mod Fire Proofing pipe and cable sleeves/penetrationsOn track | L. Haddad | 11 Sep 26 | 90% | 690 → 690 k€0.0% |
| Definition | PRJ-0105Sewer renovation North & SouthOn track | K. van Dijk | 11 Sep 26 | 55% | 668 → 668 k€0.0% |
| Definition | PRJ-0110Install PT's external pipelinesOn track | W. van Leeuwen | 27 Nov 26 | 80% | 327 → 327 k€0.0% |
| Definition | PRJ-0143Tk 1806: (Out-of-service) inspection & TTARAt risk | T. Okonkwo | 24 Jul 26 | 80% | 364 → 364 k€0.0% |
| Definition | PRJ-0165Loading arm renovationOn track | H. Nawrocki | 11 Aug 26 | 55% | 414 → 414 k€0.0% |
| Definition | PRJ-0202Mod Fire Proofing pipe and cable sleeves / penetrationsOn track | E. Vermeulen | 11 Sep 26 | 95% | 597 → 597 k€0.0% |
| Definition | PRJ-0203Foundation repairsOn track | F. de Boer | 7 Aug 26 | 35% | 560 → 560 k€0.0% |
| Definition | PRJ-0209Install PT's external pipelinesOn track | M. Bakker | 27 Nov 26 | 35% | 230 → 230 k€0.0% |
| Definition | PRJ-0211Replace PT's incl. B&B valveOn track | J. Visser | 8 Jan 27 | 95% | 293 → 293 k€0.0% |
| Definition | PRJ-0213Off-site line In-line inspection & section replacementOn track | K. van Dijk | 9 Oct 26 | 55% | 711 → 711 k€0.0% |
| Definition | PRJ-0237TK 703 - bottom plate renewalAt risk | S. de Vries | 12 Jun 26 | 55% | 485 → 485 k€0.0% |
| Definition | PRJ-0277Stair and handrail renewalOn track | I. Abdi | 7 Aug 26 | 95% | 1018 → 1018 k€0.0% |
| Definition | PRJ-0281Mod Fire Proofing lines and cable sleeves/penetrationsOn track | A. Mulder | 11 Sep 26 | 35% | 631 → 631 k€0.0% |
| Definition | PRJ-0287Install PT's external pipelinesOn track | F. de Boer | 27 Nov 26 | 35% | 239 → 239 k€0.0% |
| Execution | PRJ-0003Water treatment phase 1 HAZOP actionsAt risk | G. Smits | 16 Oct 26 | 55% | 497 → 528 k€+6.2% |
| Execution | PRJ-0004Off-site pipeline inspection off-site lineOn track | I. Abdi | 5 Feb 27 | 26% | 959 → 959 k€0.0% |
| Execution | PRJ-0005Motor control centre replacementOn track | M. Bakker | 11 Sep 26 | 43% | 875.9 → 876 k€0.0% |
| Execution | PRJ-0006E Drawings & Contractor housingOn track | S. de Vries | 11 Nov 26 | 49% | 106 → 106 k€0.0% |
| Execution | PRJ-0007Gas detection installationOn track | R. Janssen | 11 Nov 27 | 49% | 174 → 174 k€0.0% |
| Execution | PRJ-0009Reparaties manifoldsOn track | L. Haddad | 11 May 27 | 78% | 895 → 1246 k€+39.3% |
| Execution | PRJ-0010Reparaties schuim en sprenklerleidingenOn track | P. Hoekstra | 6 Nov 26 | 49% | 520 → 520 k€0.0% |
| Execution | PRJ-0012Sewer renovationOn track | D. Kramer | 18 Dec 26 | 78% | 427.4 → 427 k€0.0% |
| Execution | PRJ-00132019 Replacement LS distribution cabinetsOn track | E. Vermeulen | 10 Aug 26 | 80% | 471 → 471 k€0.0% |
| Execution | PRJ-0015Gas detection installationOn track | H. Nawrocki | 11 Sep 26 | 29% | 492 → 492 k€0.0% |
| Execution | PRJ-0019HeatwaveOn track | I. Abdi | 8 Feb 27 | 67% | 383 → 383 k€0.0% |
| Execution | PRJ-0026Replacement MOV actuators 2018On track | N. Yilmaz | 29 Jan 27 | 31% | 411 → 411 k€0.0% |
| Execution | PRJ-0027Lighting replacementOn track | D. Kramer | 2 Oct 26 | 40% | 223 → 223 k€0.0% |
| Execution | PRJ-0028Cable tray renewalOn track | E. Vermeulen | 9 Jul 27 | 47% | 1082 → 1369 k€+26.5% |
| Execution | PRJ-0037Loading arm renovationOn track | J. Visser | 27 Jul 26 | 26% | 374 → 374 k€0.0% |
| Execution | PRJ-0040High-voltage panel replacementOn track | E. Vermeulen | 7 Aug 26 | 26% | 153.6 → 177 k€+15.2% |
| Execution | PRJ-0041Pump overhaulOn track | F. de Boer | 10 Dec 26 | 43% | 400 → 400 k€0.0% |
| Execution | PRJ-0043Lighting replacementOn track | C. Peeters | 7 Aug 26 | 49% | 460 → 460 k€0.0% |
| Execution | PRJ-0044Sewer renovationOn track | W. van Leeuwen | 13 Nov 26 | 65% | 107.9 → 112 k€+3.9% |
| Execution | PRJ-0046Fire water pump repairOn track | I. Abdi | 16 Mar 27 | 80% | 85 → 85 k€0.0% |
| Execution | PRJ-0047On-site pipeline inspectionAt risk | M. Bakker | 24 Jul 26 | 25% | 176 → 176 k€0.0% |
| Execution | PRJ-0048On-site pipeline maintenanceOn track | S. de Vries | 28 Jul 26 | 29% | 227 → 227 k€0.0% |
| Execution | PRJ-0052Sewer renovationOn track | P. Hoekstra | 12 Oct 27 | 45% | 3026.3 → 3558 k€+17.6% |
| Execution | PRJ-0053Loading arm renovationOn track | N. Yilmaz | 8 Oct 26 | 44% | 221 → 221 k€0.0% |
| Execution | PRJ-0054Hydrant replacementOn track | D. Kramer | 9 Nov 26 | 52% | 148.2 → 184 k€+24.0% |
| Execution | PRJ-0055Replacement PMSX / PLC'sOn track | E. Vermeulen | 13 Aug 26 | 67% | 161 → 161 k€0.0% |
| Execution | PRJ-0056Replacement underground firewater pipelinesOn track | F. de Boer | 8 Jan 27 | 74% | 1285.8 → 1639 k€+27.5% |
| Execution | PRJ-0057Preventive maintenance backlogAt risk | H. Nawrocki | 1 May 26 | 84% | 60 → 95 k€+57.5% |
| Execution | PRJ-0060TK 1903 - vent valve replacementAt risk | S. de Vries | 24 Jul 26 | 84% | 449 → 449 k€0.0% |
| Execution | PRJ-0061TK 1905 - out-of-service inspection and repairOn track | R. Janssen | 18 Sep 26 | 25% | 364 → 364 k€0.0% |
| Execution | PRJ-0064TK 1110: (Out-of-service) inspection & TTAROn track | J. Visser | 14 Aug 26 | 47% | 534 → 534 k€0.0% |
| Execution | PRJ-0065TK 1401: (Out-of-service) inspection & TTAROn track | A. Mulder | 29 Sep 26 | 54% | 617 → 617 k€0.0% |
| Execution | PRJ-0067TK 1608: (Out-of-service) inspection & TTAROn track | P. Hoekstra | 7 Aug 26 | 77% | 435 → 435 k€0.0% |
| Execution | PRJ-0068TK 1610: (Out-of-service) inspection & TTAROn track | N. Yilmaz | 7 Aug 26 | 85% | 442 → 442 k€0.0% |
| Execution | PRJ-0070TK 1710: (Out-of-service) inspection & TTARAt risk | C. Peeters | 10 Jun 26 | 77% | 250 → 250 k€0.0% |
| Execution | PRJ-0071TK 2934: (Out-of-service) inspection & TTAROn track | W. van Leeuwen | 10 Sep 26 | 85% | 196 → 196 k€0.0% |
| Execution | PRJ-0075Tank cooling (and fire extinguishing) systemsOn track | S. de Vries | 8 Sep 26 | 49% | 1372.9 → 1373 k€0.0% |
| Execution | PRJ-0076Actuator replacementOn track | R. Janssen | 7 Aug 26 | 49% | 205 → 205 k€0.0% |
| Execution | PRJ-0077Tk 1101: (Out-of-service) inspection & TTAROn track | T. Okonkwo | 14 Aug 26 | 65% | 308 → 308 k€0.0% |
| Execution | PRJ-0078Tk 1103: (Out-of-service) inspection & TTAROn track | L. Haddad | 14 Aug 26 | 78% | 320 → 320 k€0.0% |
| Execution | PRJ-0079Tk 1105: (Out-of-service) inspection & TTAROn track | J. Visser | 14 Aug 26 | 80% | 315 → 315 k€0.0% |
| Execution | PRJ-0080Tk 1106: (Out-of-service) inspection & TTAROn track | N. Yilmaz | 14 Aug 26 | 65% | 408 → 408 k€0.0% |
| Execution | PRJ-0081Tk 1107: (Out-of-service) inspection & TTAROn track | D. Kramer | 14 Aug 26 | 78% | 456 → 456 k€0.0% |
| Execution | PRJ-0082Tk 1108: (Out-of-service) inspection & TTAROn track | E. Vermeulen | 14 Aug 26 | 80% | 450 → 450 k€0.0% |
| Execution | PRJ-0083Tk 1109: (Out-of-service) inspection & TTAROn track | F. de Boer | 14 Aug 26 | 25% | 454 → 454 k€0.0% |
| Execution | PRJ-0084Tk 1111: (Out-of-service) inspection & TTAROn track | H. Nawrocki | 17 Aug 26 | 29% | 449 → 449 k€0.0% |
| Execution | PRJ-0085Tk 1115: (Out-of-service) inspection & TTAROn track | C. Peeters | 17 Aug 26 | 45% | 453 → 453 k€0.0% |
| Execution | PRJ-0086Tk 1407: (Out-of-service) inspection & TTAROn track | W. van Leeuwen | 29 Jul 26 | 44% | 385 → 385 k€0.0% |
| Execution | PRJ-0087Tk 1709: (Out-of-service) inspection & TTARAt risk | G. Smits | 26 Jun 26 | 52% | 393 → 393 k€0.0% |
| Execution | PRJ-0088Tk 2914: (Out-of-service) inspection & TTAROn track | I. Abdi | 26 Jan 27 | 67% | 508 → 508 k€0.0% |
| Execution | PRJ-0089VRB turnaround planOn track | M. Bakker | 11 May 27 | 74% | 362 → 362 k€0.0% |
| Execution | PRJ-0090Portfolio contingencyOn track | L. Haddad | 7 Aug 26 | 52% | 200 → 200 k€0.0% |
| Execution | PRJ-0091Nitrogen blanketingOn track | J. Visser | 6 Jan 27 | 67% | 456 → 456 k€0.0% |
| Execution | PRJ-0095Updaten en aanvullen P&ID's en C&E'sOn track | N. Yilmaz | 14 May 27 | 31% | 459 → 459 k€0.0% |
| Execution | PRJ-0096Hydrant replacementOn track | D. Kramer | 1 May 26 | 40% | 76 → 76 k€0.0% |
| Execution | PRJ-0107Tank cooling (and fire extinguishing) systemsAt risk | N. Yilmaz | 15 Jun 26 | 65% | 743 → 743 k€0.0% |
| Execution | PRJ-0111Gas detection installationOn track | G. Smits | 12 Nov 27 | 78% | 392 → 392 k€0.0% |
| Execution | PRJ-0112Replacement LV distribution cabinetsOn track | I. Abdi | 13 Aug 27 | 80% | 363 → 363 k€0.0% |
| Execution | PRJ-0136TK 0803: (Out-of-service) inspection & TTAROn track | E. Vermeulen | 13 Nov 26 | 26% | 351 → 351 k€0.0% |
| Execution | PRJ-0137TK 0903: (Out-of-service) inspection & TTAR (-19 CO)On track | F. de Boer | 29 Sep 26 | 43% | 259 → 259 k€0.0% |
| Execution | PRJ-0147Ensure reliable waste water processOn track | K. van Dijk | 9 Oct 26 | 29% | 421 → 421 k€0.0% |
| Execution | PRJ-0148Replace flowmeter/computer LP7On track | P. Hoekstra | 12 Oct 26 | 45% | 808 → 808 k€0.0% |
| Execution | PRJ-0149Replacement SCADA / PLCOn track | N. Yilmaz | 14 Dec 26 | 44% | 4820 → 4820 k€0.0% |
| Execution | PRJ-0150Camera system replacementOn track | H. Nawrocki | 17 Sep 27 | 29% | 850 → 850 k€0.0% |
| Execution | PRJ-0151Fire water pump repairOn track | C. Peeters | 8 Apr 27 | 45% | 86 → 86 k€0.0% |
| Execution | PRJ-0153Bund wall repairsOn track | G. Smits | 8 Oct 27 | 52% | 2480.4 → 2586 k€+4.3% |
| Execution | PRJ-0156Cable tray renewalOn track | S. de Vries | 8 Dec 26 | 84% | 369 → 369 k€0.0% |
| Execution | PRJ-0160Maintenance charge to capexOn track | P. Hoekstra | 10 Nov 25 | 25% | 43 → 43 k€0.0% |
| Execution | PRJ-0163Foundation repairsOn track | E. Vermeulen | 11 Sep 26 | 47% | 1073 → 1073 k€0.0% |
| Execution | PRJ-0166Camera system replacementOn track | C. Peeters | 7 Aug 26 | 77% | 808.6 → 809 k€0.0% |
| Execution | PRJ-0170Waste water process improvementOn track | T. Okonkwo | 7 Aug 26 | 85% | 498 → 498 k€0.0% |
| Execution | PRJ-0171Pipework replacementOn track | L. Haddad | 10 Mar 27 | 25% | 572 → 572 k€0.0% |
| Execution | PRJ-0176Install IDDTK 708-809-810On track | N. Yilmaz | 17 Sep 27 | 65% | 268 → 268 k€0.0% |
| Execution | PRJ-0177Pump overhaulOn track | D. Kramer | 4 Jan 27 | 78% | 194 → 194 k€0.0% |
| Execution | PRJ-0178On-site pipeline inspectionOn track | E. Vermeulen | 9 Oct 26 | 80% | 182 → 182 k€0.0% |
| Execution | PRJ-0180Hydrant replacementOn track | G. Smits | 8 Jul 26 | 78% | 50 → 50 k€0.0% |
| Execution | PRJ-0182Off-site line section replacementOn track | M. Bakker | 13 Aug 26 | 25% | 364 → 364 k€0.0% |
| Execution | PRJ-0183Study and front-end engineeringOn track | S. de Vries | 10 Nov 26 | 29% | 216 → 216 k€0.0% |
| Execution | PRJ-0184Emergency shower replacementOn track | R. Janssen | 7 Aug 26 | 45% | 80 → 80 k€0.0% |
| Execution | PRJ-0185Replacement HV panel Inkoop stationOn track | T. Okonkwo | 7 Aug 26 | 44% | 252.9 → 253 k€0.0% |
| Execution | PRJ-0188Cable tray renewalOn track | A. Mulder | 5 Feb 27 | 74% | 346 → 408 k€+17.9% |
| Execution | PRJ-0190TK 305: (Out-of-service) inspection & TTAROn track | E. Vermeulen | 28 Jul 26 | 67% | 425 → 425 k€0.0% |
| Execution | PRJ-0191TK 902: (Out-of-service) inspection & TTAROn track | F. de Boer | 23 Oct 26 | 74% | 502 → 502 k€0.0% |
| Execution | PRJ-0192TK 904: (Out-of-service) inspection & TTAROn track | H. Nawrocki | 22 Oct 26 | 84% | 543 → 543 k€0.0% |
| Execution | PRJ-0194Tk 501: (Out-of-service) inspection & TTAROn track | W. van Leeuwen | 31 Aug 26 | 31% | 491 → 491 k€0.0% |
| Execution | PRJ-0195Lifting equipment inspectionOn track | G. Smits | 27 Oct 26 | 40% | 79 → 79 k€0.0% |
| Execution | PRJ-0199Updaten en aanvullen P&ID's en C&E'sOn track | R. Janssen | 13 May 27 | 77% | 434 → 434 k€0.0% |
| Execution | PRJ-0206Tank cooling (and fire extinguishing) systemsOn track | W. van Leeuwen | 14 Apr 27 | 65% | 653 → 653 k€0.0% |
| Execution | PRJ-0208Access control high/low voltage stationsOn track | I. Abdi | 11 Dec 26 | 80% | 189 → 189 k€0.0% |
| Execution | PRJ-0212Cable tray renewalOn track | A. Mulder | 12 Nov 27 | 25% | 357 → 357 k€0.0% |
| Execution | PRJ-0222TK 0208: (Out-of-service) inspection & TTAROn track | S. de Vries | 14 Aug 26 | 84% | 379 → 379 k€0.0% |
| Execution | PRJ-0226TK 0608: (Out-of-service) inspection & TTAROn track | J. Visser | 7 Aug 26 | 47% | 385 → 385 k€0.0% |
| Execution | PRJ-0229Level measurement replacementOn track | P. Hoekstra | 5 Feb 27 | 77% | 580 → 580 k€0.0% |
| Execution | PRJ-0230Camera system replacementOn track | F. de Boer | 5 Feb 27 | 54% | 1412 → 1412 k€0.0% |
| Execution | PRJ-0233Low-voltage distribution cabinet replacementOn track | W. van Leeuwen | 9 Oct 26 | 85% | 662 → 662 k€0.0% |
| Execution | PRJ-0236Cable tray renewalOn track | M. Bakker | 7 Aug 26 | 43% | 260 → 260 k€0.0% |
| Execution | PRJ-0243Vapour recovery modificationOn track | D. Kramer | 7 Aug 26 | 78% | 424 → 424 k€0.0% |
| Execution | PRJ-0244Pit 6 N2 incl. permanente zuurstofbewakinOn track | E. Vermeulen | 9 Sep 26 | 80% | 420 → 420 k€0.0% |
| Execution | PRJ-0247Closed pigcatcher systemOn track | C. Peeters | 10 Nov 26 | 45% | 170 → 170 k€0.0% |
| Execution | PRJ-0248Building maintenanceOn track | W. van Leeuwen | 7 Aug 26 | 44% | 197.4 → 197 k€0.0% |
| Execution | PRJ-0249Mixer overhaulOn track | G. Smits | 11 Sep 26 | 52% | 479 → 479 k€0.0% |
| Execution | PRJ-0255Insulation renewalOn track | K. van Dijk | 11 Sep 26 | 84% | 172 → 172 k€0.0% |
| Execution | PRJ-0256On-site pipeline inspectionOn track | P. Hoekstra | 9 Oct 26 | 25% | 200 → 200 k€0.0% |
| Execution | PRJ-0260Cable tray renewalOn track | W. van Leeuwen | 10 Aug 26 | 31% | 31.1 → 31 k€0.0% |
| Execution | PRJ-0265SHEQ improvement budgetOn track | R. Janssen | 10 Sep 26 | 77% | 68 → 68 k€0.0% |
| Execution | PRJ-0267Lighting replacementOn track | L. Haddad | 5 Feb 27 | 25% | 339 → 339 k€0.0% |
| Execution | PRJ-0268TK 204: (Out-of-service) inspection & TTAROn track | J. Visser | 7 Aug 26 | 26% | 407 → 407 k€0.0% |
| Execution | PRJ-0270TK 805: (Out-of-service) inspection & TTAROn track | D. Kramer | 3 Sep 26 | 25% | 446 → 446 k€0.0% |
| Execution | PRJ-0275Updaten en aanvullen P&ID's en C&E'sOn track | W. van Leeuwen | 11 May 27 | 65% | 447 → 447 k€0.0% |
| Execution | PRJ-0283Tank cooling (and fire extinguishing) systemsOn track | P. Hoekstra | 14 May 27 | 45% | 670 → 670 k€0.0% |
| Execution | PRJ-0285Access control high/low voltage stationsOn track | D. Kramer | 11 Dec 26 | 52% | 184 → 184 k€0.0% |
| Execution | PRJ-0288High-voltage panel replacementOn track | H. Nawrocki | 12 Nov 27 | 84% | 287 → 287 k€0.0% |
| Execution | PRJ-0296TK 0113: (Out-of-service) inspection & TTAROn track | A. Mulder | 2 Oct 26 | 54% | 334 → 334 k€0.0% |
| Execution | PRJ-0298TK 0407: (Out-of-service) inspection & TTAROn track | P. Hoekstra | 2 Oct 26 | 77% | 421 → 421 k€0.0% |
| Close-out | PRJ-0001Pump overhaulOn track | C. Peeters | 11 Sep 26 | 68% | 564 → 564 k€0.0% |
| Close-out | PRJ-0002Tank 2101: Inspection + Repair +MaintenanceOn track | W. van Leeuwen | 12 Jun 26 | 69% | 601 → 601 k€0.0% |
| Close-out | PRJ-0008Maintenance activities offices and buildingOn track | T. Okonkwo | 15 May 26 | 49% | 96 → 96 k€0.0% |
| Close-out | PRJ-0011Fire water pump repairOn track | N. Yilmaz | 25 Nov 25 | 49% | 84 → 84 k€0.0% |
| Close-out | PRJ-0016TK 1712 - roof drain replacementOn track | C. Peeters | 15 Jun 26 | 68% | 572 → 572 k€0.0% |
| Close-out | PRJ-0017TK 1802 - bottom plate renewalOn track | W. van Leeuwen | 4 Aug 26 | 69% | 556 → 556 k€0.0% |
| Close-out | PRJ-0020Cable tray renewalOn track | T. Okonkwo | 15 Oct 26 | 69% | 145 → 145 k€0.0% |
| Close-out | PRJ-0021Jetty repairOn track | L. Haddad | 11 Sep 26 | 43% | 1459.3 → 1459 k€0.0% |
| Close-out | PRJ-0022Mechanical modifications during TTAROn track | J. Visser | 8 May 26 | 41% | 268 → 268 k€0.0% |
| Close-out | PRJ-0023Emergency shower replacementOn track | A. Mulder | 8 May 26 | 65% | 55 → 55 k€0.0% |
| Close-out | PRJ-0024Renovation marine loading armsBlocked | K. van Dijk | 13 Apr 26 | 66% | 274 → 274 k€0.0% |
| Close-out | PRJ-0029Preventive maintenance backlogOn track | F. de Boer | 6 Feb 26 | 36% | 62 → 62 k€0.0% |
| Close-out | PRJ-0030SHEQ ImprovementOn track | G. Smits | 28 May 26 | 61% | 77 → 77 k€0.0% |
| Close-out | PRJ-0033TK 402 - floating roof seal replacementOn track | S. de Vries | 19 Jun 26 | 46% | 438 → 438 k€0.0% |
| Close-out | PRJ-0034Tank cooling (and fire extinguishing) systeOn track | R. Janssen | 3 Jul 26 | 68% | 1337.6 → 1338 k€0.0% |
| Close-out | PRJ-0036Preventive maintenance backlogAt risk | L. Haddad | 10 Jul 26 | 43% | 105 → 105 k€0.0% |
| Close-out | PRJ-0038Crane overhaulAt risk | A. Mulder | 5 Jun 26 | 65% | 399 → 399 k€0.0% |
| Close-out | PRJ-0045Loading arm renovationAt risk | G. Smits | 16 Jun 26 | 61% | 363 → 363 k€0.0% |
| Close-out | PRJ-0051Lighting replacementOn track | K. van Dijk | 17 Jul 26 | 46% | 42.1 → 42 k€0.0% |
| Close-out | PRJ-0058SHEQ improvement budgetOn track | C. Peeters | 12 Jun 26 | 40% | 55 → 55 k€0.0% |
| Close-out | PRJ-0062Crane overhaulOn track | T. Okonkwo | 24 Aug 26 | 49% | 239 → 239 k€0.0% |
| Close-out | PRJ-0063TK 1104: (Out-of-service) inspection & TTAROn track | L. Haddad | 23 Oct 26 | 61% | 462 → 462 k€0.0% |
| Close-out | PRJ-0066TK 1404: (Out-of-service) inspection & TTAROn track | K. van Dijk | 16 Sep 26 | 46% | 402 → 402 k€0.0% |
| Close-out | PRJ-0069TK 1706: (Out-of-service) inspection & TTAROn track | D. Kramer | 4 Sep 26 | 43% | 601 → 601 k€0.0% |
| Close-out | PRJ-0072TK 301: (Out-of-service) inspection & TTAROn track | G. Smits | 7 Jul 26 | 43% | 207 → 207 k€0.0% |
| Close-out | PRJ-0073TK 311: (Out-of-service) inspection & TTAROn track | I. Abdi | 14 Sep 26 | 41% | 270 → 270 k€0.0% |
| Close-out | PRJ-0074TK 505: (Out-of-service) inspection & TTAROn track | M. Bakker | 3 Jul 26 | 65% | 213 → 213 k€0.0% |
| Close-out | PRJ-0092Actuator replacementOn track | A. Mulder | 30 Jul 26 | 65% | 351 → 351 k€0.0% |
| Close-out | PRJ-0094Uitwendig conserveren tankdak 501On track | P. Hoekstra | 25 Jun 26 | 40% | 422 → 422 k€0.0% |
| Close-out | PRJ-0152Hydrant replacementOn track | W. van Leeuwen | 6 Nov 26 | 69% | 69 → 69 k€0.0% |
| Close-out | PRJ-0155Foundation repairsOn track | M. Bakker | 12 Jun 26 | 65% | 819 → 819 k€0.0% |
| Close-out | PRJ-0158Fire proofing of structuresOn track | T. Okonkwo | 7 Aug 26 | 49% | 933.5 → 934 k€0.0% |
| Close-out | PRJ-0159Cathodic protection upgradeOn track | L. Haddad | 13 Aug 26 | 61% | 547 → 547 k€0.0% |
| Close-out | PRJ-0161On-site pipeline maintenanceOn track | N. Yilmaz | 10 Jul 26 | 49% | 381 → 381 k€0.0% |
| Close-out | PRJ-0162Painting tanksOn track | D. Kramer | 3 Sep 26 | 61% | 79 → 79 k€0.0% |
| Close-out | PRJ-0167Lifting equipment inspectionOn track | W. van Leeuwen | 7 Jul 26 | 69% | 93 → 93 k€0.0% |
| Close-out | PRJ-0169Preventive maintenance backlogOn track | I. Abdi | 22 Jun 26 | 41% | 35 → 35 k€0.0% |
| Close-out | PRJ-0172TTAR Tank 309On track | J. Visser | 12 Jun 26 | 41% | 581 → 581 k€0.0% |
| Close-out | PRJ-0173Level measurement replacementOn track | A. Mulder | 19 May 26 | 65% | 206 → 206 k€0.0% |
| Close-out | PRJ-0175In Service (On Stream) InspectionOn track | P. Hoekstra | 8 May 26 | 40% | 416 → 416 k€0.0% |
| Close-out | PRJ-0179On-site pipeline maintenanceOn track | F. de Boer | 11 Sep 26 | 36% | 177 → 177 k€0.0% |
| Close-out | PRJ-0186Fire water pump repairOn track | L. Haddad | 26 Jun 26 | 43% | 30 → 30 k€0.0% |
| Close-out | PRJ-0187SHEQ improvement budgetOn track | J. Visser | 26 Jun 26 | 41% | 62.5 → 63 k€0.0% |
| Close-out | PRJ-0189Motor control centre replacementOn track | K. van Dijk | 21 Aug 26 | 77% | 232 → 232 k€0.0% |
| Close-out | PRJ-0193Tank cooling (and fire extinguishing) systemsOn track | C. Peeters | 17 Jul 26 | 40% | 253.8 → 254 k€0.0% |
| Close-out | PRJ-0196Painting and coating programmeOn track | I. Abdi | 26 Jun 26 | 74% | 75 → 75 k€0.0% |
| Close-out | PRJ-0197Level measurement replacementOn track | M. Bakker | 2 Jul 26 | 36% | 162 → 162 k€0.0% |
| Close-out | PRJ-0231Operating computer replacementAt risk | H. Nawrocki | 17 Jul 26 | 46% | 191 → 191 k€0.0% |
| Close-out | PRJ-0232Replacement MCC's pump roomsOn track | C. Peeters | 12 Aug 26 | 68% | 390 → 390 k€0.0% |
| Close-out | PRJ-0235Lighting replacementOn track | I. Abdi | 10 Jul 26 | 41% | 344 → 344 k€0.0% |
| Close-out | PRJ-0238Off-site line inspectionOn track | R. Janssen | 13 Aug 26 | 40% | 594 → 594 k€0.0% |
| Close-out | PRJ-0239Maintenance charge to capexOn track | T. Okonkwo | 13 Nov 25 | 49% | 153 → 153 k€0.0% |
| Close-out | PRJ-0240Painting tanksOn track | K. van Dijk | 7 Jul 26 | 77% | 80 → 80 k€0.0% |
| Close-out | PRJ-0245Tank cooling (and fire extinguishing) systeOn track | F. de Boer | 13 Jul 26 | 36% | 425 → 425 k€0.0% |
| Close-out | PRJ-0246Thermische expansie tankleidingenOn track | H. Nawrocki | 4 Sep 26 | 46% | 443 → 443 k€0.0% |
| Close-out | PRJ-0250Terminal automation upgradeOn track | R. Janssen | 19 May 26 | 68% | 93 → 93 k€0.0% |
| Close-out | PRJ-0251Out-of-service inspection and repairOn track | T. Okonkwo | 3 Jul 26 | 69% | 231 → 231 k€0.0% |
| Close-out | PRJ-0252In service (On Stream) InspectionsOn track | L. Haddad | 10 Jul 26 | 43% | 213 → 213 k€0.0% |
| Close-out | PRJ-0253Loading arm renovationOn track | J. Visser | 16 Jun 26 | 41% | 161 → 161 k€0.0% |
| Close-out | PRJ-0257On-site pipeline maintenanceOn track | N. Yilmaz | 11 Sep 26 | 49% | 194 → 194 k€0.0% |
| Close-out | PRJ-0258Concrete repairs to roads and hardstandingOn track | D. Kramer | 31 Jul 26 | 61% | 540 → 540 k€0.0% |
| Close-out | PRJ-0262Replace camera systemOn track | I. Abdi | 21 Aug 26 | 74% | 682.3 → 682 k€0.0% |
| Close-out | PRJ-0263Gas detection installationOn track | M. Bakker | 10 Sep 26 | 36% | 79.6 → 80 k€0.0% |
| Close-out | PRJ-0264Replacement Lighting workplacesOn track | S. de Vries | 11 Nov 26 | 46% | 176.6 → 177 k€0.0% |
| Close-out | PRJ-0269TK 511: (Out-of-service) inspection & TTAROn track | A. Mulder | 8 Oct 26 | 65% | 376 → 376 k€0.0% |
| Close-out | PRJ-0271Tank cooling (and fire extinguishing) systemsOn track | E. Vermeulen | 18 Jun 26 | 41% | 322.9 → 323 k€0.0% |
| Close-out | PRJ-0273Painting and coating programmeAt risk | H. Nawrocki | 10 Jul 26 | 77% | 200 → 200 k€0.0% |
| Close-out | PRJ-0274Terminal automation upgradeOn track | C. Peeters | 23 Jul 26 | 40% | 176 → 176 k€0.0% |
| Close-out | PRJ-0276Actuator replacementOn track | G. Smits | 10 Jul 26 | 61% | 343 → 343 k€0.0% |