Project manager

153 new·585 open

Reports →
WhatProjectThe lineSinceAnswerNote
New since the review of 14 Jul 26153
Over budgetPRJ-0003Water treatment phase 1 HAZOP actionsG. SmitsForecast over the approved budget+31 k€ · +6.2%was +16 k€ at the last review25 Jul 26
Over budgetPRJ-0009Reparaties manifoldsL. HaddadForecast over the approved budget+351 k€ · +39.3%was +176 k€ at the last review25 Jul 26
Claim openPRJ-0258Concrete repairs to roads and hardstandingD. KramerWrong material delivered — replacement flanges and rework+11.5 k€25 Jul 26not agreed
Date passedPRJ-0055Replacement PMSX / PLC'sE. VermeulenMC1 days late24 Jul 26
Date passedPRJ-0086Tk 1407: (Out-of-service) inspection & TTARW. van LeeuwenRFO forms1 days late24 Jul 26
Claim openPRJ-0092Actuator replacementA. MulderWrong material delivered — replacement flanges and rework+11.5 k€24 Jul 26not agreed
Key date movedPRJ-0112Replacement LV distribution cabinetsI. AbdiRFO+8 days · P. Hoekstra2027-08-0424 Jul 26
Date passedPRJ-0190TK 305: (Out-of-service) inspection & TTARE. VermeulenCommissioning1 days late24 Jul 26
Date passedPRJ-0238Off-site line inspectionR. JanssenAs-built1 days late24 Jul 26
Key date movedPRJ-0255Insulation renewalK. van DijkRFO+4 days · G. Smits2026-08-2824 Jul 26
Date passedPRJ-0274Terminal automation upgradeC. PeetersFinancial1 days late24 Jul 26
Date passedPRJ-0032Pig catcher replacementM. BakkerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0040High-voltage panel replacementE. VermeulenCommissioning2 days late23 Jul 26
Claim openPRJ-0040High-voltage panel replacementE. VermeulenStandby — work permit not issued on time+5.6 k€23 Jul 26open
Key date movedPRJ-0041Pump overhaulF. de BoerMC+13 days · S. de Vries2026-11-0723 Jul 26
Date passedPRJ-0043Lighting replacementC. PeetersCommissioning2 days late23 Jul 26
Claim openPRJ-0043Lighting replacementC. PeetersStandby — work permit not issued on time+4.0 k€23 Jul 26open
Date passedPRJ-0048On-site pipeline maintenanceS. de VriesRFO forms2 days late23 Jul 26
Key date movedPRJ-0048On-site pipeline maintenanceS. de VriesStart construction+7 days · K. van Dijk2026-07-0423 Jul 26
Date passedPRJ-0067TK 1608: (Out-of-service) inspection & TTARP. HoekstraCommissioning2 days late23 Jul 26
Key date movedPRJ-0067TK 1608: (Out-of-service) inspection & TTARP. HoekstraMC+9 days · W. van Leeuwen2026-07-0923 Jul 26
Claim openPRJ-0067TK 1608: (Out-of-service) inspection & TTARP. HoekstraStandby — work permit not issued on time+4.8 k€23 Jul 26open
Claim openPRJ-0068TK 1610: (Out-of-service) inspection & TTARN. YilmazStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0076Actuator replacementR. JanssenCommissioning2 days late23 Jul 26
Claim openPRJ-0076Actuator replacementR. JanssenStandby — work permit not issued on time+4.8 k€23 Jul 26open
Date passedPRJ-0085Tk 1115: (Out-of-service) inspection & TTARC. PeetersStart construction2 days late23 Jul 26
Claim openPRJ-0086Tk 1407: (Out-of-service) inspection & TTARW. van LeeuwenWrong material delivered — replacement flanges and rework+11.5 k€23 Jul 26open
Date passedPRJ-0090Portfolio contingencyL. HaddadCommissioning2 days late23 Jul 26
Claim openPRJ-0090Portfolio contingencyL. HaddadStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0117On-site pipeline maintenanceL. HaddadBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0118Pipe sleeves/penetrations replacementJ. VisserBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0120Pig catcher replacementD. KramerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0122Waste water process improvementF. de BoerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0124In Service (On Stream) InspectionsC. PeetersBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0125TK 1907 - shell plate repairsW. van LeeuwenBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0126Replacement P8 water treatmentG. SmitsBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0127Gas detection installationI. AbdiBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0128Portfolio contingencyM. BakkerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0140TK 1604: (Out-of-service) inspection & TTARM. BakkerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0145TK 2005: On-Stream inspectionJ. VisserBid + 40% estimate2 days late23 Jul 26
Claim openPRJ-0158Fire proofing of structuresT. OkonkwoStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0166Camera system replacementC. PeetersCommissioning2 days late23 Jul 26
Claim openPRJ-0166Camera system replacementC. PeetersStandby — work permit not issued on time+4.8 k€23 Jul 26open
Date passedPRJ-0168Painting and coating programmeG. SmitsBid + 40% estimate2 days late23 Jul 26
Claim openPRJ-0170Waste water process improvementT. OkonkwoStandby — work permit not issued on time+4.8 k€23 Jul 26open
Date passedPRJ-0174Lifting equipment inspectionK. van DijkBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0184Emergency shower replacementR. JanssenCommissioning2 days late23 Jul 26
Key date movedPRJ-0184Emergency shower replacementR. JanssenMC+9 days · N. Yilmaz2026-07-0923 Jul 26
Claim openPRJ-0184Emergency shower replacementR. JanssenStandby — work permit not issued on time+4.8 k€23 Jul 26open
Date passedPRJ-0185Replacement HV panel Inkoop stationT. OkonkwoCommissioning2 days late23 Jul 26
Claim openPRJ-0185Replacement HV panel Inkoop stationT. OkonkwoStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0190TK 305: (Out-of-service) inspection & TTARE. VermeulenRFO forms2 days late23 Jul 26
Date passedPRJ-0214Replace tourniquetP. HoekstraBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0217SHEQ improvement budgetE. VermeulenBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0220Install floating roof seals'TK 708/809/810I. AbdiBid + 40% estimate2 days late23 Jul 26
Claim openPRJ-0226TK 0608: (Out-of-service) inspection & TTARJ. VisserStandby — work permit not issued on time+6.4 k€23 Jul 26open
Date passedPRJ-0236Cable tray renewalM. BakkerCommissioning2 days late23 Jul 26
Claim openPRJ-0236Cable tray renewalM. BakkerStandby — work permit not issued on time+3.2 k€23 Jul 26open
Date passedPRJ-0242TK 310 - internal coating renewalN. YilmazBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0243Vapour recovery modificationD. KramerCommissioning2 days late23 Jul 26
Claim openPRJ-0243Vapour recovery modificationD. KramerStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0248Building maintenanceW. van LeeuwenCommissioning2 days late23 Jul 26
Claim openPRJ-0248Building maintenanceW. van LeeuwenStandby — work permit not issued on time+5.6 k€23 Jul 26open
Date passedPRJ-0268TK 204: (Out-of-service) inspection & TTARJ. VisserCommissioning2 days late23 Jul 26
Claim openPRJ-0268TK 204: (Out-of-service) inspection & TTARJ. VisserStandby — work permit not issued on time+3.2 k€23 Jul 26open
Date passedPRJ-0278Hydrant replacementM. BakkerBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0280Concrete plates railJ. VisserBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0282Stairways and handrailing adjust/addK. van DijkBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0284Fire water pump repairN. YilmazBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0289Fence repairC. PeetersBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0293Study N2 bufferingT. OkonkwoBid + 40% estimate2 days late23 Jul 26
Date passedPRJ-0037Loading arm renovationJ. VisserRFO forms3 days late22 Jul 26
Claim openPRJ-0048On-site pipeline maintenanceS. de VriesWrong material delivered — replacement flanges and rework+11.5 k€22 Jul 26open
Date passedPRJ-0103Retaining wall repairsJ. VisserBid + 40% estimate3 days late22 Jul 26
Claim openPRJ-0190TK 305: (Out-of-service) inspection & TTARE. VermeulenWrong material delivered — replacement flanges and rework+11.5 k€22 Jul 26open
Date passedPRJ-0194Tk 501: (Out-of-service) inspection & TTARW. van LeeuwenRFC3 days late22 Jul 26
Date passedPRJ-0268TK 204: (Out-of-service) inspection & TTARJ. VisserMC3 days late22 Jul 26
Claim openPRJ-0037Loading arm renovationJ. VisserWrong material delivered — replacement flanges and rework+11.5 k€21 Jul 26open
Key date movedPRJ-0076Actuator replacementR. JanssenRFC+11 days · J. Visser2026-06-1721 Jul 26
Date passedPRJ-0258Concrete repairs to roads and hardstandingD. KramerFinancial4 days late21 Jul 26
Date passedPRJ-0260Cable tray renewalW. van LeeuwenMC4 days late21 Jul 26
Key date movedPRJ-0003Water treatment phase 1 HAZOP actionsG. SmitsMC+14 days · G. Smits2026-09-0420 Jul 26
Key date movedPRJ-0003Water treatment phase 1 HAZOP actionsG. SmitsRFO+14 days · G. Smits2026-09-2520 Jul 26
Claim openPRJ-0017TK 1802 - bottom plate renewalW. van LeeuwenStandby — work permit not issued on time+4.8 k€20 Jul 26open
Date passedPRJ-0031Building maintenanceI. AbdiBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0049Bund wall repairsR. JanssenBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0059TK 1902 - mixer overhaulW. van LeeuwenBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0064TK 1110: (Out-of-service) inspection & TTARJ. VisserStart construction5 days late20 Jul 26
Key date movedPRJ-0082Tk 1108: (Out-of-service) inspection & TTARE. VermeulenRFO+8 days · R. Janssen2026-07-2720 Jul 26
Date passedPRJ-0083Tk 1109: (Out-of-service) inspection & TTARF. de BoerStart construction5 days late20 Jul 26
Date passedPRJ-0092Actuator replacementA. MulderFinancial5 days late20 Jul 26
Date passedPRJ-0116On-site pipeline inspectionT. OkonkwoBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0121Nitrogen blanketingE. VermeulenBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0139TTAR Tank 1408C. PeetersBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0154Painting and coating programmeI. AbdiBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0157Study and front-end engineeringR. JanssenBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0215On-site pipeline inspectionN. YilmazBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0216On-site pipeline maintenanceD. KramerBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0219In Service (On Stream) InspectionsH. NawrockiBid + 40% estimate5 days late20 Jul 26
Key date movedPRJ-0233Low-voltage distribution cabinet replacementW. van LeeuwenRFO+12 days · A. Mulder2026-09-1720 Jul 26
Date passedPRJ-0234Building maintenanceG. SmitsBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0261Emergency shower replacementG. SmitsBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0291On-site pipeline inspectionS. de VriesBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0292On-site pipeline maintenanceR. JanssenBid + 40% estimate5 days late20 Jul 26
Date passedPRJ-0294In service (On Stream) InspectionsL. HaddadBid + 40% estimate5 days late20 Jul 26
Key date movedPRJ-0026Replacement MOV actuators 2018N. YilmazStart construction+3 days · W. van Leeuwen2027-01-0119 Jul 26
Date passedPRJ-0047On-site pipeline inspectionM. BakkerRFO forms6 days late19 Jul 26
Date passedPRJ-0060TK 1903 - vent valve replacementS. de VriesRFO forms6 days late19 Jul 26
Date passedPRJ-0143Tk 1806: (Out-of-service) inspection & TTART. OkonkwoDetail engineering + 10% estimate6 days late19 Jul 26
Date passedPRJ-0182Off-site line section replacementM. BakkerStart construction6 days late19 Jul 26
Key date movedPRJ-0188Cable tray renewalA. MulderMC+13 days · H. Nawrocki2027-01-0319 Jul 26
Date passedPRJ-0238Off-site line inspectionR. JanssenPunch list6 days late19 Jul 26
Key date movedPRJ-0260Cable tray renewalW. van LeeuwenStart construction+3 days · T. Okonkwo2026-07-1319 Jul 26
Date passedPRJ-0040High-voltage panel replacementE. VermeulenMC7 days late18 Jul 26
Date passedPRJ-0043Lighting replacementC. PeetersMC7 days late18 Jul 26
Claim openPRJ-0047On-site pipeline inspectionM. BakkerWrong material delivered — replacement flanges and rework+11.5 k€18 Jul 26not agreed
Date passedPRJ-0048On-site pipeline maintenanceS. de VriesRFO7 days late18 Jul 26
Over budgetPRJ-0054Hydrant replacementD. KramerForecast over the approved budget+36 k€ · +24.0%was +18 k€ at the last review18 Jul 26
Over budgetPRJ-0057Preventive maintenance backlogH. NawrockiForecast over the approved budget+35 k€ · +57.5%was +17 k€ at the last review18 Jul 26
Claim openPRJ-0060TK 1903 - vent valve replacementS. de VriesWrong material delivered — replacement flanges and rework+11.5 k€18 Jul 26open
Date passedPRJ-0076Actuator replacementR. JanssenMC7 days late18 Jul 26
Date passedPRJ-0084Tk 1111: (Out-of-service) inspection & TTARH. NawrockiLOTO plans7 days late18 Jul 26
Date passedPRJ-0090Portfolio contingencyL. HaddadMC7 days late18 Jul 26
Over budgetPRJ-0153Bund wall repairsG. SmitsForecast over the approved budget+106 k€ · +4.3%was +53 k€ at the last review18 Jul 26
Date passedPRJ-0158Fire proofing of structuresT. OkonkwoAs-built7 days late18 Jul 26
Date passedPRJ-0184Emergency shower replacementR. JanssenMC7 days late18 Jul 26
Date passedPRJ-0185Replacement HV panel Inkoop stationT. OkonkwoMC7 days late18 Jul 26
Date passedPRJ-0190TK 305: (Out-of-service) inspection & TTARE. VermeulenRFO7 days late18 Jul 26
Date passedPRJ-0193Tank cooling (and fire extinguishing) systemsC. PeetersFinancial7 days late18 Jul 26
Date passedPRJ-0226TK 0608: (Out-of-service) inspection & TTARJ. VisserMC7 days late18 Jul 26
Date passedPRJ-0248Building maintenanceW. van LeeuwenMC7 days late18 Jul 26
Date passedPRJ-0274Terminal automation upgradeC. PeetersClose-out7 days late18 Jul 26
Date passedPRJ-0037Loading arm renovationJ. VisserCommissioning8 days late17 Jul 26
Date passedPRJ-0037Loading arm renovationJ. VisserRFO8 days late17 Jul 26
Key date movedPRJ-0054Hydrant replacementD. KramerRFC+7 days · H. Nawrocki2026-09-2317 Jul 26
Key date movedPRJ-0171Pipework replacementL. HaddadRFC+7 days · K. van Dijk2027-01-2217 Jul 26
Claim openPRJ-0274Terminal automation upgradeC. PeetersWrong material delivered — replacement flanges and rework+11.5 k€17 Jul 26not agreed
Claim openPRJ-0003Water treatment phase 1 HAZOP actionsG. SmitsSecond dosing pump added to scope+12.0 k€16 Jul 26open
Date passedPRJ-0043Lighting replacementC. PeetersStart construction9 days late16 Jul 26
Key date movedPRJ-0060TK 1903 - vent valve replacementS. de VriesRFO+4 days · D. Kramer2026-07-1016 Jul 26
Key date movedPRJ-0086Tk 1407: (Out-of-service) inspection & TTARW. van LeeuwenRFO+12 days · A. Mulder2026-07-1416 Jul 26
Date passedPRJ-0184Emergency shower replacementR. JanssenLOTO plans9 days late16 Jul 26
Date passedPRJ-0258Concrete repairs to roads and hardstandingD. KramerEvaluation9 days late16 Jul 26
Claim openPRJ-0258Concrete repairs to roads and hardstandingD. KramerStandby — work permit not issued on time+6.4 k€16 Jul 26open
Date passedPRJ-0260Cable tray renewalW. van LeeuwenStart construction9 days late16 Jul 26
Date passedPRJ-0273Painting and coating programmeH. NawrockiClose-out9 days late16 Jul 26
Key date movedPRJ-0004Off-site pipeline inspection off-site lineI. AbdiStart construction+11 days · J. Visser2026-12-3115 Jul 26
Date passedPRJ-0064TK 1110: (Out-of-service) inspection & TTARJ. VisserLOTO plans10 days late15 Jul 26
Date passedPRJ-0092Actuator replacementA. MulderEvaluation10 days late15 Jul 26
Claim openPRJ-0092Actuator replacementA. MulderStandby — work permit not issued on time+3.2 k€15 Jul 26open
Key date movedPRJ-0147Ensure reliable waste water processK. van DijkStart construction+7 days · H. Nawrocki2026-09-1215 Jul 26
Key date movedPRJ-0166Camera system replacementC. PeetersMC+9 days · T. Okonkwo2026-07-0915 Jul 26
Key date movedPRJ-0283Tank cooling (and fire extinguishing) systemsP. HoekstraMC+9 days · W. van Leeuwen2027-04-1515 Jul 26
Was new at the review of 7 Jul 2659
Standing longer373· been through more than one meeting — oldest first
ReviewLast closed 14 Jul 26·153 things have happened since