Week 2225 May – 31 May
PlannedCompletedEarlier week — not yet reported complete
WorkorderStartHoursDiscipline
Crusher CR-1 — liner inspection25 May4hMech · Insp
Mill 1 drive gearbox — oil sample + filter swap25 May4hMech · Insp
Conveyor C-15 — replace head pulley bearing25 May4hElec · Mech
Vessel V-301 — internal cleaning & inspection25 May7.5hMech
Mill Mill 1 — liner replacement25 May8hMech
Compressor K-2 — vibration follow-up25 May2hInsp
PT-502 — pressure transmitter calibration25 May2hMech · Inst
Pump P-205 — impeller swap26 May6hElec · Mech
Mill Mill 2 — liner replacement26 May8hMech
Valve V-412 — actuator stroke test26 May2hMech · Inst
Heat exchanger E-12 — full tube bundle overhaul26 May8hMech · Insp
Crusher CR-2 gearbox — oil sample + filter swap26 May4hMech · Insp
Compressor K-3 — rotor rebuild26 May8hElec · Mech
Conveyor C-12 — replace head pulley bearing26 May4hElec · Mech
Switchgear SG-1 — annual inspection27 May3hElec · Insp
Heat exchanger E-31 — tube inspection27 May5hMech · Insp
Compressor K-1 — rotor rebuild27 May8hElec · Mech
Valve V-220 — actuator stroke test27 May2hMech · Inst
Heat exchanger E-22 — full tube bundle overhaul27 May8hMech · Insp
Valve V-118 — actuator stroke test27 May2hMech · Inst
Pump P-118 — impeller swap27 May6hElec · Mech
Pump P-205 — vibration follow-up27 May2hInsp
Flow meter FT-301 — verification28 May2hInst
Vessel S-12 — internal cleaning & inspection28 May7.5hMech
Flow meter FT-208 — verification28 May2hInst
Conveyor C-21 — replace head pulley bearing28 May4hElec · Mech
Compressor K-4 — coupling alignment29 May4hElec · Mech
Switchgear SG-1 — thermal scan29 May3hElec · Insp
Heat exchanger E-44 — tube inspection29 May5hMech · Insp
Mon 25 May
Tue 26 May
Wed 27 May
Thu 28 May
Fri 29 May
Sat30
Sun31