Planboard
Weekly workorder planning per discipline
Week 48: Nov 23 – Nov 27, 2026
Add Work
10
Show discipline
Mechanical
Electrical
Instrumentation
Rotating
Mon
23
Nov
M
10h
E
9h
I
1h
R
0h
14h blocked
Print
Tue
24
Nov
M
25h
E
18h
I
2h
R
0h
30h blocked
Print
Wed
25
Nov
M
10h
E
7h
I
2h
R
0h
12h blocked
Print
Thu
26
Nov
M
12h
E
9h
I
2h
R
0h
6h blocked
Print
Fri
27
Nov
M
9h
E
5h
I
3h
R
0h
5h blocked
Print
Replace mechanical seal — Pump P-2201A
M
→
E
→
M
→
E
M 4h
·
E 4h
Isolation not yet removed
Planned as standby work. Execute if time is available.
Thermographic inspection MCC panel — E-1200
E
→
M
M 2h
·
E 2h
Planned as standby work. Execute if time is available.
Calibrate pressure transmitter PT-3310
I
→
M
→
I
M 1h
·
I 1h
Planned as standby work. Execute if time is available.
CML thickness measurement — vessel V-1601
M
→
E
→
M
→
E
M 3h
·
E 3h
Workpermit not yet approved
Planned as standby work. Execute if time is available.
Inspect and re-grease bearings — Fan F-1102
M
→
E
M 2h
·
E 2h
Planned as standby work. Execute if time is available.
Overhaul compressor valve assembly — K-301
M
→
E
→
M
M 11h
·
E 5h
Isolation not yet removed
Scaffolding not yet placed
Planned as standby work. Execute if time is available.
Replace contactor — Motor M-2204
E
→
M
→
E
M 1h
·
E 2h
Planned as standby work. Execute if time is available.
Replace level transmitter LT-1407
I
→
M
→
I
→
M
M 2h
·
I 2h
Scaffolding not yet placed
Planned as standby work. Execute if time is available.
Visual inspection welds — pipeline section 7A
M
→
E
M 4h
·
E 4h
Planned as standby work. Execute if time is available.
Pipe support repair — rack area 2 elevation 6m
M
→
E
M 5h
·
E 5h
Scaffolding not yet placed
Planned as standby work. Execute if time is available.
Replace coupling insert — Pump P-4405B
M
→
E
→
M
→
E
M 2h
·
E 2h
Planned as standby work. Execute if time is available.
Earth fault loop test — HV substation 3B
E
→
M
→
E
→
M
M 4h
·
E 4h
Workpermit not yet approved
Planned as standby work. Execute if time is available.
Functional test — ESD valve XV-2201
I
→
M
M 2h
·
I 2h
Planned as standby work. Execute if time is available.
Safety valve inspection SV-3302
M
→
E
→
M
M 3h
·
E 1h
Isolation not yet removed
Workpermit not yet approved
Planned as standby work. Execute if time is available.
PM — lubrication round agitator AG-502
M
→
E
M 1h
·
E 1h
Planned as standby work. Execute if time is available.
UPS battery capacity test — control room
E
→
M
M 2h
·
E 2h
Planned as standby work. Execute if time is available.
Flow meter verification FT-0812
I
→
M
→
I
M 1h
·
I 2h
Planned as standby work. Execute if time is available.
Corrosion inspection heat exchanger E-2101
M
→
E
→
M
→
E
M 3h
·
E 3h
Scaffolding not yet placed
Planned as standby work. Execute if time is available.
Floor grating replacement — platform P-09
M
→
E
→
M
M 5h
·
E 3h
Planned as standby work. Execute if time is available.
Vibration check — rotating equipment area 3
M
→
E
→
M
M 4h
·
E 2h
Planned as standby work. Execute if time is available.
Cable insulation resistance test — area 5
E
→
M
→
E
M 2h
·
E 3h
Workpermit not yet approved
Planned as standby work. Execute if time is available.
Calibrate analysers — online GC unit 4
I
→
M
→
I
→
M
M 3h
·
I 3h
Planned as standby work. Execute if time is available.
3 aging workorders outrank newer scheduled work
•
Only 24 hours for mechanical work ready to schedule
•
Only 4 hours for electrical work ready to schedule
•
Only 2 hours for instrumentation work ready to schedule